nerdexam
(ISC)2

CAP · Question #44

You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the…

The correct answer is D. Risk register updates. According to the PMBOK Guide, the single output of the Perform Quantitative Risk Analysis process is Risk Register Updates. The quantitative analysis (using techniques like Monte Carlo simulation, decision tree analysis, or sensitivity analysis) produces numerical data about…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager of the NKQ project for your organization. You have completed the quantitative risk analysis process for this portion of the project. What is the only output of the quantitative risk analysis process?

Options

  • AProbability of reaching project objectives
  • BRisk contingency reserve
  • CRisk response
  • DRisk register updates

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    7% (2)
  • D
    89% (25)

Explanation

According to the PMBOK Guide, the single output of the Perform Quantitative Risk Analysis process is Risk Register Updates. The quantitative analysis (using techniques like Monte Carlo simulation, decision tree analysis, or sensitivity analysis) produces numerical data about overall project risk and probability of meeting objectives. All findings - including probability of achieving cost/schedule targets, contingency reserve recommendations, and prioritized risk lists - are documented as updates to the risk register, not as separate standalone outputs.

Topics

#Risk Management#Quantitative Risk Analysis#Project Management#Risk Register

Community Discussion

No community discussion yet for this question.

Full CAP Practice