The correct answer is B: System or process flowcharts. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager of QSL project for your organization. You are working you're your project team and several key stakeholders to create a diagram that shows how various elements of a system interrelate and the mechanism of causation within the system. What diagramming technique are you using as a part of the risk identification process?

Options

  • ACause and effect diagrams
  • BSystem or process flowcharts
  • CPredecessor and successor diagramming
  • DInfluence diagrams

Topics

#Risk Identification#System Flowcharts#Risk Management Process

Community Discussion

No community discussion yet for this question.