Which one of the following is the only output for the qualitative risk analysis process?
The correct answer is B. Risk register updates. In the PMBOK framework, the Qualitative Risk Analysis process has a single output: Risk Register Updates. After qualitative analysis, the risk register is updated with each risk's probability rating, impact rating, overall risk score, priority ranking, and risk categorization…
Question
Which one of the following is the only output for the qualitative risk analysis process?
Options
- AProject management plan
- BRisk register updates
- CEnterprise environmental factors
- DOrganizational process assets
How the community answered
(23 responses)- A4% (1)
- B91% (21)
- C4% (1)
Explanation
In the PMBOK framework, the Qualitative Risk Analysis process has a single output: Risk Register Updates. After qualitative analysis, the risk register is updated with each risk's probability rating, impact rating, overall risk score, priority ranking, and risk categorization. The other choices are inputs, not outputs: the Project Management Plan and Risk Register are inputs that inform the analysis; Enterprise Environmental Factors and Organizational Process Assets are also inputs that provide context (e.g., industry risk databases, historical project data).