Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?

The correct answer is A. Stakeholder register. The standard inputs to the Qualitative Risk Analysis process (per PMBOK) are the Risk Register (list of identified risks), the Risk Management Plan (probability/impact matrix, risk categories, definitions), the Project Scope Statement (complex or novel scope increases uncertainty

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Wendy is about to perform qualitative risk analysis on the identified risks within her project. Which one of the following will NOT help Wendy to perform this project management activity?

Options

  • AStakeholder register
  • BRisk register
  • CProject scope statement
  • DRisk management plan

How the community answered

(32 responses)
  • A
    75% (24)
  • B
    3% (1)
  • C
    6% (2)
  • D
    16% (5)

Explanation

The standard inputs to the Qualitative Risk Analysis process (per PMBOK) are the Risk Register (list of identified risks), the Risk Management Plan (probability/impact matrix, risk categories, definitions), the Project Scope Statement (complex or novel scope increases uncertainty), and organizational process assets/enterprise environmental factors. The Stakeholder Register is an input to stakeholder management and communications planning processes - not to qualitative risk analysis. It tells you who the stakeholders are, not how to assess or prioritize risks.

Topics

#Qualitative Risk Analysis#Risk Management Process#Project Management Documents#Risk Register