CAP · Question #374

CAP Question #374: Real Exam Question with Answer & Explanation

The correct answer is A: List of potential responses. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

Options

  • AList of potential responses
  • BList of identified risks
  • CList ofmitigation techniques
  • DList of key stakeholders

Topics

#Risk Management Process#Risk Register Contents#Risk Identification#Risk Responses