You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct…

The correct answer is A. List of potential responses B. List of identified risks. The risk register is the primary output of the Identify Risks process and initially contains: (A) a list of potential risk responses - preliminary response ideas captured during identification, and (B) a list of identified risks - descriptions of each risk event. A 'list of…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager for TTP project. You are in the Identify Risks process. You have to create the risk register. Which of the following are included in the risk register? Each correct answer represents a complete solution. Choose two.

Options

  • AList of potential responses
  • BList of identified risks
  • CList ofmitigation techniques
  • DList of key stakeholders

How the community answered

(32 responses)
  • A
    91% (29)
  • C
    6% (2)
  • D
    3% (1)

Explanation

The risk register is the primary output of the Identify Risks process and initially contains: (A) a list of potential risk responses - preliminary response ideas captured during identification, and (B) a list of identified risks - descriptions of each risk event. A 'list of mitigation techniques' (C) implies detailed risk response planning, which comes later in the Plan Risk Responses process. A 'list of key stakeholders' (D) belongs in the stakeholder register, not the risk register.

Topics

#Risk Management Process#Risk Register Contents#Risk Identification#Risk Responses