You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example
The correct answer is C. Sharing. Risk Sharing (C) involves partnering with another party to jointly pursue an opportunity or divide the burden of a risk. A teaming agreement - where two or more organizations formally agree to collaborate - is a classic example of sharing, because both parties share the potential
Question
You are the project manager of the HJK project for your organization. You and the project team have created risk responses for many of the risk events in the project. A teaming agreement is an example of what risk response?
Options
- AAcceptance
- BMitigation
- CSharing
- DTransference
How the community answered
(41 responses)- A5% (2)
- B5% (2)
- C88% (36)
- D2% (1)
Explanation
Risk Sharing (C) involves partnering with another party to jointly pursue an opportunity or divide the burden of a risk. A teaming agreement - where two or more organizations formally agree to collaborate - is a classic example of sharing, because both parties share the potential upside and downside. Transference (D) shifts the financial consequence to a third party (e.g., insurance) but does not involve joint participation. Mitigation (B) reduces probability or impact. Acceptance (A) means doing nothing proactively.