nerdexam
(ISC)2

CAP · Question #358

What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

The correct answer is D. Risk management plan. The Risk Management Plan defines how risk management activities will be structured and performed throughout the project, including the methodologies, tools, data sources, timing, and roles for processes like quantitative risk analysis. It directly directs how quantitative analysi

Security and Privacy Governance, Risk Management, and Compliance Program

Question

What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

Options

  • AStaffing management plan
  • BRisk analysis plan
  • CHuman resource management plan
  • DRisk management plan

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    10% (2)
  • D
    85% (17)

Explanation

The Risk Management Plan defines how risk management activities will be structured and performed throughout the project, including the methodologies, tools, data sources, timing, and roles for processes like quantitative risk analysis. It directly directs how quantitative analysis (e.g., Monte Carlo simulations, expected monetary value) is to be conducted. In a matrix environment, resource complexity is higher, but the plan governing risk analysis remains the Risk Management Plan. The staffing and human resource management plans address personnel allocation, not risk analysis methodology.

Topics

#Risk Management#Project Management#Quantitative Risk Analysis#Project Planning

Community Discussion

No community discussion yet for this question.

Full CAP Practice