CAP · Question #358
CAP Question #358: Real Exam Question with Answer & Explanation
The correct answer is D: Risk management plan. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?
Options
- AStaffing management plan
- BRisk analysis plan
- CHuman resource management plan
- DRisk management plan
Topics
#Risk Management#Project Management#Quantitative Risk Analysis#Project Planning