nerdexam
(ISC)2

CAP · Question #337

You are the project manager of the GGH Project in your company. Your company is structured as a functional organization and you report to the functional manager that you are ready to move onto the…

The correct answer is C. You will need the risk register, risk management plan, cost management plan, schedule. The inputs to the Quantitative Risk Analysis process (per PMBOK) include the risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets - regardless of organizational structure. The functional organization structure…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager of the GGH Project in your company. Your company is structured as a functional organization and you report to the functional manager that you are ready to move onto the quantitative risk analysis process. What things will you need as inputs for the quantitative risk analysis of the project in this scenario?

Options

  • AYou will need the risk register, risk management plan, permission from the functional
  • BYou will need the risk register, risk management plan, outputs of qualitative risk analysis, and
  • CYou will need the risk register, risk management plan, cost management plan, schedule
  • DQuantitative risk analysis does not happen through the project manager in a functional stru

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    87% (34)
  • D
    3% (1)

Explanation

The inputs to the Quantitative Risk Analysis process (per PMBOK) include the risk register, risk management plan, cost management plan, schedule management plan, and organizational process assets - regardless of organizational structure. The functional organization structure does not change the required inputs (eliminating D). Option A incorrectly adds 'permission from the functional manager' as an input (organizational politics are not a formal process input). Option B is incomplete and vague. Option C correctly identifies the core inputs: risk register + risk management plan + cost management plan + schedule management plan, which together provide the data needed for numerical risk modeling (Monte Carlo simulations, decision tree analysis, etc.).

Topics

#Quantitative Risk Analysis#Risk Management Inputs#Project Management#Functional Organization

Community Discussion

No community discussion yet for this question.

Full CAP Practice