nerdexam
(ISC)2(ISC)2

CAP · Question #246

CAP Question #246: Real Exam Question with Answer & Explanation

The correct answer is C: Project management plan. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?

Options

  • AProject contractual relationship with the vendor
  • BProject communications plan
  • CProject management plan
  • DProject scope statement

Topics

#Risk Management#Project Management Plan#Risk Response#Project Updates

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions