nerdexam
(ISC)2

CAP · Question #240

Which one of the following is the only output for the qualitative risk analysis process?

The correct answer is C. Risk register updates. According to the PMBOK Guide, the Perform Qualitative Risk Analysis process has a single output: Risk Register Updates. After qualitative analysis, the risk register is updated to include risk probability and impact ratings, risk scores, risk rankings, risk urgency assessments…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Which one of the following is the only output for the qualitative risk analysis process?

Options

  • AEnterprise environmental factors
  • BProject management plan
  • CRisk register updates
  • DOrganizational process assets

How the community answered

(41 responses)
  • A
    2% (1)
  • C
    93% (38)
  • D
    5% (2)

Explanation

According to the PMBOK Guide, the Perform Qualitative Risk Analysis process has a single output: Risk Register Updates. After qualitative analysis, the risk register is updated to include risk probability and impact ratings, risk scores, risk rankings, risk urgency assessments, and a watch list of low-priority risks. Enterprise environmental factors, the project management plan, and organizational process assets are all inputs to (not outputs of) the Perform Qualitative Risk Analysis process. This makes Risk Register Updates the sole, definitive output of this process.

Topics

#Risk Management#Qualitative Risk Analysis#Risk Register

Community Discussion

No community discussion yet for this question.

Full CAP Practice