CAP · Question #236
Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new…
The correct answer is B. Monitor and Control Risks. The description precisely matches the Monitor and Control Risks process from the PMBOK Guide. This is an ongoing, iterative process in the Monitoring and Controlling process group that tracks identified risks, watches for trigger conditions, implements response plans, evaluates…
Question
Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."
Options
- APerform Quantitative Risk Analysis
- BMonitor and Control Risks
- CPerform Qualitative Risk Analysis
- DIdentify Risks
How the community answered
(40 responses)- A3% (1)
- B88% (35)
- C8% (3)
- D3% (1)
Explanation
The description precisely matches the Monitor and Control Risks process from the PMBOK Guide. This is an ongoing, iterative process in the Monitoring and Controlling process group that tracks identified risks, watches for trigger conditions, implements response plans, evaluates their effectiveness, and identifies newly emerging risks. Perform Qualitative Risk Analysis prioritizes risks by probability and impact. Perform Quantitative Risk Analysis numerically analyzes the effect of risk on objectives. Identify Risks is about initially discovering and documenting potential risks-not monitoring or controlling them.