nerdexam
(ISC)2(ISC)2

CAP · Question #233

CAP Question #233: Real Exam Question with Answer & Explanation

The correct answer is D: It depends on what the terminationclause of the contract stipulates. See the full explanation below for the reasoning.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Eric is the project manager of the NQQ Project and has hired the ZAS Corporation to complete part of the project work for Eric's organization. Due to a change request the ZAS Corporation is no longer needed on the project even though they have completed nearly all of the project work. Is Eric's organization liable to pay the ZAS Corporation for the work they have completed so far on the project?

Options

  • ANo, the ZAS Corporation did not complete all of the work.
  • BYes, the ZAS Corporation did not choose to terminate the contract work.
  • CIt depends on what the outcome of a lawsuit will determine.
  • DIt depends on what the terminationclause of the contract stipulates

Topics

#Contract management#Vendor management#Termination clauses#Project liability

Community Discussion

No community discussion yet for this question.

Full CAP PracticeBrowse All CAP Questions