Which of the following is not a part of Identify Risks process?

The correct answer is A. Decision tree diagram. The Identify Risks process uses diagramming techniques such as cause-and-effect (Ishikawa/fishbone) diagrams, influence diagrams, and system or process flow charts to uncover potential risks. A decision tree diagram is a tool used in Perform Quantitative Risk Analysis, not in Ide

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Which of the following is not a part of Identify Risks process?

Options

  • ADecision tree diagram
  • BCause and effect diagram
  • CInfluence diagram
  • DSystem or process flow chart

How the community answered

(58 responses)
  • A
    95% (55)
  • B
    2% (1)
  • C
    2% (1)
  • D
    2% (1)

Explanation

The Identify Risks process uses diagramming techniques such as cause-and-effect (Ishikawa/fishbone) diagrams, influence diagrams, and system or process flow charts to uncover potential risks. A decision tree diagram is a tool used in Perform Quantitative Risk Analysis, not in Identify Risks. Decision trees help calculate expected monetary value (EMV) of different decision paths, which is a quantitative, not identification-phase, activity.

Topics

#Risk Identification Techniques#Risk Management Process#Decision Analysis Tools