CAP · Question #203
Which of the following is not a part of Identify Risks process?
The correct answer is A. Decision tree diagram. The Identify Risks process uses diagramming techniques such as cause-and-effect (Ishikawa/fishbone) diagrams, influence diagrams, and system or process flow charts to uncover potential risks. A decision tree diagram is a tool used in Perform Quantitative Risk Analysis, not in Ide
Question
Which of the following is not a part of Identify Risks process?
Options
- ADecision tree diagram
- BCause and effect diagram
- CInfluence diagram
- DSystem or process flow chart
How the community answered
(58 responses)- A95% (55)
- B2% (1)
- C2% (1)
- D2% (1)
Explanation
The Identify Risks process uses diagramming techniques such as cause-and-effect (Ishikawa/fishbone) diagrams, influence diagrams, and system or process flow charts to uncover potential risks. A decision tree diagram is a tool used in Perform Quantitative Risk Analysis, not in Identify Risks. Decision trees help calculate expected monetary value (EMV) of different decision paths, which is a quantitative, not identification-phase, activity.
Topics