You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your…

The correct answer is A. Qualitative risk analysis. Qualitative Risk Analysis (A) is specifically designed to provide a rapid and cost-effective means for establishing priorities for risk responses. It uses probability and impact assessments (often in a probability-impact matrix) to rank risks subjectively without requiring…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?

Options

  • AQualitative risk analysis
  • BQuantitative analysis
  • CHistorical information
  • DRolling wave planning

How the community answered

(40 responses)
  • A
    73% (29)
  • B
    18% (7)
  • C
    3% (1)
  • D
    8% (3)

Explanation

Qualitative Risk Analysis (A) is specifically designed to provide a rapid and cost-effective means for establishing priorities for risk responses. It uses probability and impact assessments (often in a probability-impact matrix) to rank risks subjectively without requiring detailed numerical analysis. Quantitative Analysis (B) is more rigorous and time-consuming, using numerical techniques like Monte Carlo simulation. Historical information (C) is an input to risk processes, not a process itself. Rolling wave planning (D) is a progressive elaboration planning technique, not a risk management process.

Topics

#Risk management processes#Qualitative risk analysis#Risk prioritization#Cost-effective risk analysis