CAP · Question #188
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your…
The correct answer is A. Qualitative risk analysis. Qualitative Risk Analysis (A) is specifically designed to provide a rapid and cost-effective means for establishing priorities for risk responses. It uses probability and impact assessments (often in a probability-impact matrix) to rank risks subjectively without requiring…
Question
You work as a project manager for BlueWell Inc. You are working on a project and the management wants a rapid and cost-effective means for establishing priorities for planning risk responses in your project. Which risk management process can satisfy management's objective for your project?
Options
- AQualitative risk analysis
- BQuantitative analysis
- CHistorical information
- DRolling wave planning
How the community answered
(40 responses)- A73% (29)
- B18% (7)
- C3% (1)
- D8% (3)
Explanation
Qualitative Risk Analysis (A) is specifically designed to provide a rapid and cost-effective means for establishing priorities for risk responses. It uses probability and impact assessments (often in a probability-impact matrix) to rank risks subjectively without requiring detailed numerical analysis. Quantitative Analysis (B) is more rigorous and time-consuming, using numerical techniques like Monte Carlo simulation. Historical information (C) is an input to risk processes, not a process itself. Rolling wave planning (D) is a progressive elaboration planning technique, not a risk management process.