CAP · Question #183
The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.
The correct answer is A. Quantitative Risk Analysis C. Risk Monitoring and Control D. Risk Management Planning. The correct answers are A (Quantitative Risk Analysis), C (Risk Monitoring and Control), and D (Risk Management Planning). According to PMBOK, the Project Risk Management knowledge area includes: Plan Risk Management, Identify Risks, Perform Qualitative Risk Analysis, Perform…
Question
The Project Risk Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.
Options
- AQuantitative Risk Analysis
- BPotential Risk Monitoring
- CRisk Monitoring and Control
- DRisk Management Planning
How the community answered
(16 responses)- A94% (15)
- B6% (1)
Explanation
The correct answers are A (Quantitative Risk Analysis), C (Risk Monitoring and Control), and D (Risk Management Planning). According to PMBOK, the Project Risk Management knowledge area includes: Plan Risk Management, Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, Plan Risk Responses, and Monitor/Control Risks. 'Potential Risk Monitoring' (B) is not a recognized PMBOK process name - it is a fabricated distractor. All three correct options correspond directly to named processes within the knowledge area.