CAP · Question #181
CAP Question #181: Real Exam Question with Answer & Explanation
Sign in or unlock CAP to reveal the answer and full explanation for question #181. The question stem and answer options stay visible for context.
Question
Your project team has identified a project risk that must be responded to. The risk has been recorded in the risk register and the project team has been discussing potential risk responses for the risk event. The event is not likely to happen for several months but the probability of the event is high. Which one of the following is a valid response to the identified risk event?
Options
- ACorrective action
- BTechnical performance measurement
- CRisk audit
- DEarned value management