CAP · Question #151
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she an
The correct answer is D. The events should be entered into the risk register.. Newly discovered risk events during any risk analysis process must first be logged in the risk register before any further action is taken.
Question
Jenny is the project manager for the NBT projects. She is working with the project team and several subject matter experts to perform the quantitative risk analysis process. During this process she and the project team uncover several risks events that were not previously identified. What should Jenny do with these risk events?
Options
- AThe events should be determined if they need to be accepted or responded to.
- BThe events should be entered into qualitative risk analysis.
- CThe events should continue on with quantitative risk analysis.
- DThe events should be entered into the risk register.
How the community answered
(23 responses)- A4% (1)
- B13% (3)
- C9% (2)
- D74% (17)
Why each option
Newly discovered risk events during any risk analysis process must first be logged in the risk register before any further action is taken.
Deciding to accept or respond to a risk is a risk response planning activity that occurs after the risk has been formally identified and documented in the risk register.
Entering risks directly into qualitative risk analysis skips the required step of first documenting them in the risk register.
Continuing quantitative risk analysis on newly discovered risks bypasses the formal identification and registration step required for all risks.
The risk register is the central repository for all identified risks throughout the project lifecycle. Any new risk event discovered - even during quantitative risk analysis - must be entered into the risk register first so it can be formally tracked, analyzed, and assigned a response. Skipping this step means the risk lacks the documentation needed for subsequent planning or monitoring.
Concept tested: Risk register as repository for newly identified risks
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
No community discussion yet for this question.