Question
Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders - including management. Mark will need to update all of the following information except for which one?
Options
- AWatchlist of low-priority risks
- BPrioritized list of quantified risks
- CRisks grouped by categories
- DTrends in qualitative risk analysis