nerdexam
(ISC)2(ISC)2

CAP · Question #148

CAP Question #148: Real Exam Question with Answer & Explanation

Sign in or unlock CAP to reveal the answer and full explanation for question #148. The question stem and answer options stay visible for context.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Mark works as a project manager for TechSoft Inc. Mark, the project team, and the key project stakeholders have completed a round of qualitative risk analysis. He needs to update the risk register with his findings so that he can communicate the risk results to the project stakeholders - including management. Mark will need to update all of the following information except for which one?

Options

  • AWatchlist of low-priority risks
  • BPrioritized list of quantified risks
  • CRisks grouped by categories
  • DTrends in qualitative risk analysis

Unlock CAP to see the answer

You've previewed enough free CAP questions. Unlock CAP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Qualitative Risk Analysis#Risk Register Updates#Risk Communication
Full CAP PracticeBrowse All CAP Questions