CAP · Question #143

Which types of project tends to have more well-understood risks?

The correct answer is B. Recurrent projects. Recurrent projects - those that have been performed before - tend to have more well-understood risks because the project team and organization can draw on historical data, lessons learned, and prior experience from similar projects. In contrast, state-of-the-art technology…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Which types of project tends to have more well-understood risks?

Options

  • AState-of-art technologyprojects
  • BRecurrent projects
  • COperational work projects
  • DFirst-of-its kind technology projects

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    85% (22)
  • C
    4% (1)
  • D
    4% (1)

Explanation

Recurrent projects - those that have been performed before - tend to have more well-understood risks because the project team and organization can draw on historical data, lessons learned, and prior experience from similar projects. In contrast, state-of-the-art technology projects and first-of-its-kind technology projects involve novel or untested components, meaning risks are less predictable and harder to anticipate. Operational work is ongoing and routine but is not the same as a project. Recurrent projects benefit from pattern recognition, making risk identification, probability estimation, and impact assessment more reliable.

Topics

#Project Management#Risk Management#Project Types#Risk Assessment

Community Discussion

No community discussion yet for this question.