Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this…

The correct answer is D. Sammy is correct, because organizations can create risk scores for each objective of the pr. Sammy is correct because PMBOK allows organizations to assess risk probability and impact against each individual project objective - time, cost, and scope - separately.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

Sammy is the project manager for her organization. She would like to rate each risk based on its probability and affect on time, cost, and scope. Harry, a project team member, has never done this before and thinks Sammy is wrong to attempt this approach. Harry says that an accumulative risk score should be created, not three separate risk scores. Who is correct in this scenario?

Options

  • AHarry is correct, because the risk probability and impact considers all objectives of the proj
  • BHarry is correct, the risk probability and impact matrix is the only approach to risk assessm
  • CSammy is correct, because sheis the project manager.
  • DSammy is correct, because organizations can create risk scores for each objective of the pr

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    12% (3)
  • D
    77% (20)

Why each option

Sammy is correct because PMBOK allows organizations to assess risk probability and impact against each individual project objective - time, cost, and scope - separately.

AHarry is correct, because the risk probability and impact considers all objectives of the proj

Harry's claim that risk probability and impact must always consider all objectives cumulatively is incorrect; PMBOK supports per-objective scoring as a valid alternative.

BHarry is correct, the risk probability and impact matrix is the only approach to risk assessm

The risk probability and impact matrix is one tool among many for risk assessment, not the exclusive or mandatory approach.

CSammy is correct, because sheis the project manager.

Being the project manager does not by itself make Sammy correct; the answer requires a valid technical justification, not an appeal to authority.

DSammy is correct, because organizations can create risk scores for each objective of the prCorrect

PMBOK explicitly allows organizations to evaluate risks against each project objective individually, producing separate risk scores for time, cost, scope, and quality. This approach provides more granular insight into how a specific risk may affect different aspects of the project differently. Creating separate scores is a recognized and valid approach, not a methodological error as Harry suggests.

Concept tested: Risk probability and impact assessment per project objective

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Risk Management#Risk Assessment#Risk Scoring#Project Objectives