CAP · Question #114

You work as a project manager for TechSoft Inc. You are working with the project stakeholders onthe qualitative risk analysis process in your project. You have used all the tools to the qualitative…

The correct answer is A. Risk Reassessment. Risk reassessment is a tool used in the Monitor and Control Risks process, not in the qualitative risk analysis process.

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for TechSoft Inc. You are working with the project stakeholders onthe qualitative risk analysis process in your project. You have used all the tools to the qualitative risk analysis process in your project. Which of the following techniques is NOT used as a tool in qualitative risk analysis process?

Options

  • ARisk Reassessment
  • BRisk Categorization
  • CRisk Urgency Assessment
  • DRisk Data Quality Assessment

How the community answered

(35 responses)
  • A
    86% (30)
  • B
    3% (1)
  • C
    9% (3)
  • D
    3% (1)

Why each option

Risk reassessment is a tool used in the Monitor and Control Risks process, not in the qualitative risk analysis process.

ARisk ReassessmentCorrect

Risk reassessment involves re-evaluating current risks and identifying new risks, which is an activity that belongs to the Monitor Risks process (previously called Monitor and Control Risks). The tools and techniques of qualitative risk analysis are risk data quality assessment, risk categorization, risk urgency assessment, risk probability and impact assessment, the probability and impact matrix, and expert judgment - risk reassessment is not among them.

BRisk Categorization

Risk categorization is a legitimate tool of qualitative risk analysis used to group risks by source or area for more effective analysis.

CRisk Urgency Assessment

Risk urgency assessment is used in qualitative analysis to identify risks requiring near-term responses based on their time sensitivity.

DRisk Data Quality Assessment

Risk data quality assessment is used in qualitative risk analysis to evaluate the accuracy and reliability of risk data before analysis proceeds.

Concept tested: Tools and techniques of qualitative risk analysis

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Qualitative Risk Analysis#Risk Management Process#Risk Assessment Tools#Project Risk Management