What are the preparatory setting for using Task and Resource Management? (Choose three)

The correct answer is A. The central organizational unit of TRM i.e. site C. The spatial factors of the warehouse complex are mapped in a two-dimensional site map D. Defining which stock movement are relevant to TRM. See the full explanation below for the reasoning.

Question

What are the preparatory setting for using Task and Resource Management? (Choose three)

Options

  • AThe central organizational unit of TRM i.e. site
  • BThe spatial factors of the warehouse complex are mapped in a three-dimensional site map
  • CThe spatial factors of the warehouse complex are mapped in a two-dimensional site map
  • DDefining which stock movement are relevant to TRM
  • EAll the above