We are using precise scheduling to process the orders. Which of the following statements not correct? (Choose two)
The correct answer is A. In precise scheduling, the system uses days, hours, and minutes, but only displays the resulting C. Precise scheduling uses the factory calendar of the shipping point to determine the transportation. See the full explanation below for the reasoning.
Question
We are using precise scheduling to process the orders. Which of the following statements not correct? (Choose two)
Options
- AIn precise scheduling, the system uses days, hours, and minutes, but only displays the resulting
- BThe system performs precise scheduling if we have maintained the working hours of the shipping
- CPrecise scheduling uses the factory calendar of the shipping point to determine the transportation
- DPrecise scheduling uses the factory calendar of the route to determine the transit time
- EIn precise scheduling, the system calculates and displays the results of scheduling down to the
How the community answered
(24 responses)- A71% (17)
- B17% (4)
- D8% (2)
- E4% (1)