C_TSCM62_66 · Question #86

What is a prerequisite for using down payments in an integrated SD-FI down payment process?

The correct answer is D. A sales order must be created with a milestone billing plan that contains the required down. See the full explanation below for the reasoning.

Question

What is a prerequisite for using down payments in an integrated SD-FI down payment process?

Options

  • AA sales order must be created with an installment plan that uses terms of payment to control the
  • BThe requested down payment is determined as a separate item in the sales order by using item
  • CThe standard billing type F2 must be used in the billing plan for the down payment.
  • DA sales order must be created with a milestone billing plan that contains the required down

How the community answered

(19 responses)
  • B
    11% (2)
  • C
    5% (1)
  • D
    84% (16)