C_TSCM62_66 · Question #86
What is a prerequisite for using down payments in an integrated SD-FI down payment process?
The correct answer is D. A sales order must be created with a milestone billing plan that contains the required down. See the full explanation below for the reasoning.
Question
What is a prerequisite for using down payments in an integrated SD-FI down payment process?
Options
- AA sales order must be created with an installment plan that uses terms of payment to control the
- BThe requested down payment is determined as a separate item in the sales order by using item
- CThe standard billing type F2 must be used in the billing plan for the down payment.
- DA sales order must be created with a milestone billing plan that contains the required down
How the community answered
(19 responses)- B11% (2)
- C5% (1)
- D84% (16)