Which of the following can be used to determine the schedule line category?
The correct answer is A. Item category. See the full explanation below for the reasoning.
Question
Which of the following can be used to determine the schedule line category?
Options
- AItem category
- BItem category with "Schedule Line allowed" indicator and MRP type
- CMRP type
- DItem category and document type
How the community answered
(35 responses)- A71% (25)
- B9% (3)
- C17% (6)
- D3% (1)