C_TSCM62_66 · Question #49

C_TSCM62_66 Question #49: Real Exam Question with Answer & Explanation

Sign in or unlock C_TSCM62_66 to reveal the answer and full explanation for question #49. The question stem and answer options stay visible for context.

Question

Which of the following statements regarding delivery and transportation scheduling are correct? (Choose two)

Options

  • AThe transportation lead time, pick/pack time, loading time, and transit time are taken into account
  • BThe delivery and transportation dates determined in the order are visible at header level.
  • COn the calculated post goods issue date, the material requirements of the item are transferred to
  • DWhen the requested delivery date cannot be confirmed by backward scheduling, the order can