What are the consequences when you change the payer at header level in a sales order? (Choose two)

The correct answer is A. Any additional sales order items are given the payment terms for the new payer. C. Receivables resulting from the sales order are posted to the new payer. See the full explanation below for the reasoning.

Question

What are the consequences when you change the payer at header level in a sales order? (Choose two)

Options

  • AAny additional sales order items are given the payment terms for the new payer.
  • BThe partner function "Payer" is changed in the sold-to customer master.
  • CReceivables resulting from the sales order are posted to the new payer.
  • DThe billing document (invoice) is automatically sent to the new payer.

How the community answered

(35 responses)
  • A
    80% (28)
  • B
    9% (3)
  • D
    11% (4)