Which of the following settings in Customizing do you have to maintain for a scheduling agreement?

The correct answer is A. A schedule line category. See the full explanation below for the reasoning.

Question

Which of the following settings in Customizing do you have to maintain for a scheduling agreement?

Options

  • AA schedule line category
  • BA product hierarchy
  • CA billing plan
  • DThe copying control for the release order

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    4% (1)
  • C
    8% (2)
  • D
    4% (1)