For which of the following objects can you use a standard movement type to post a goods issue directly from the valuated stock? There are 3 correct answers to this question. Response:
The correct answer is B. Production order C. Project (WBS element) D. Cost center. See the full explanation below for the reasoning.
Question
For which of the following objects can you use a standard movement type to post a goods issue directly from the valuated stock? There are 3 correct answers to this question. Response:
Options
- AProfit center
- BProduction order
- CProject (WBS element)
- DCost center