nerdexam
SAP

C_TSCM52_67 · Question #182

What procurement proposals can be generated during the MRP run? There are 3 correct answers to this question. Response:

The correct answer is A. Purchase requisitions B. Schedule lines D. Planned orders. See the full explanation below for the reasoning.

Question

What procurement proposals can be generated during the MRP run? There are 3 correct answers to this question. Response:

Options

  • APurchase requisitions
  • BSchedule lines
  • CQuantity contracts
  • DPlanned orders
  • EPurchase orders

How the community answered

(22 responses)
  • A
    73% (16)
  • C
    9% (2)
  • E
    18% (4)

Community Discussion

No community discussion yet for this question.

Full C_TSCM52_67 Practice