C_TSCM52_64 · Question #27
You perform a total planning run for a plant. On the initial screen, you can select a creation indicator for MRP lists. Which of the following can determine whether an MRP list is created for a…
The correct answer is B. Exception message. See the full explanation below for the reasoning.
Question
You perform a total planning run for a plant. On the initial screen, you can select a creation indicator for MRP lists. Which of the following can determine whether an MRP list is created for a material?
Options
- AProcurement type
- BException message
- CMRP type
- DMRP controller
How the community answered
(28 responses)- A7% (2)
- B82% (23)
- C4% (1)
- D7% (2)
Community Discussion