Which times belong to the replenishment lead time in the planning run for an externally procured material? (Choose three.)
The correct answer is A. Purchasing processing time B. Planned delivery time D. Goods receipt processing time. See the full explanation below for the reasoning.
Question
Which times belong to the replenishment lead time in the planning run for an externally procured material? (Choose three.)
Options
- APurchasing processing time
- BPlanned delivery time
- CRequirement lead time
- DGoods receipt processing time
- EMinimum remaining shelf life
How the community answered
(20 responses)- A75% (15)
- C10% (2)
- E15% (3)