C_TSCM44_65 · Question #84
C_TSCM44_65 Question #84: Real Exam Question with Answer & Explanation
Sign in or unlock C_TSCM44_65 to reveal the answer and full explanation for question #84. The question stem and answer options stay visible for context.
Question
Within the global parameters and default values the "plan explosion" is set to "explode production process model (PPM)". Your master data team would like to switch from PPM to PDS over the next 12 months as part of an ongoing redesign project. Is it possible to configure the system to explode the PDS for product "A" yet still explode the PPM for product "B"?
Options
- AYes. As soon as a PDS is integrated via the CIF, the corresponding APO product master is
- BNo. Since the SNP planning module could also be in use, the plan explosion always needs to
- CYes. In model and version management you have to define the product-specific master data
- DNo. The master data project has to be harmonized with the APO planning project that is