C_TSCM44_65 · Question #8
How can you back up planning data to the internal BW?
The correct answer is D. Create a DataSource for the planning area and connect it to an InfoCube. See the full explanation below for the reasoning.
Question
How can you back up planning data to the internal BW?
Options
- ACreate a VirtualProvider for the planning area and connect it to an InfoCube.
- BUse transaction /SAPAPO/TSCUBE-Load Data from InfoCube.
- CCreate a DataSource for the planning area and connect it to a VirtualProvider.
- DCreate a DataSource for the planning area and connect it to an InfoCube.
How the community answered
(42 responses)- A2% (1)
- B12% (5)
- C7% (3)
- D79% (33)