SAP
C_TSCM44_65 · Question #67
Various background jobs can be scheduled in DP. What is the correct configuration sequence when scheduling a background job in DP?
The correct answer is C. To run a forecast you need a profile, an activity, and a job. See the full explanation below for the reasoning.
Question
Various background jobs can be scheduled in DP. What is the correct configuration sequence when scheduling a background job in DP?
Options
- ATo create proportional factors you need a profile, an activity, and a job.
- BTo run a macro you need a profile, an activity, and a job.
- CTo run a forecast you need a profile, an activity, and a job.
- DTo run a release you need an activity and a job.
How the community answered
(38 responses)- A5% (2)
- B3% (1)
- C84% (32)
- D8% (3)
Community Discussion
No community discussion yet for this question.