C_TSCM44_65 · Question #58
Your customer runs an integrated system landscape including SAP ECC and SAP SCM and wants to specify a firming interval of 10 working days that rolls forward over time for an APO- relevant finished…
The correct answer is B. Set the planning time fence to 10 days in the corresponding ECC material master. D. Set the planning time fence to 10 days in the corresponding ECC MRP group. See the full explanation below for the reasoning.
Question
Your customer runs an integrated system landscape including SAP ECC and SAP SCM and wants to specify a firming interval of 10 working days that rolls forward over time for an APO- relevant finished product. Which of the following settings lead to this result? Note: There are 2 correct answers to this question.
Options
- ASet the planning time fence in the APO product view to 10 days in the future.
- BSet the planning time fence to 10 days in the corresponding ECC material master.
- CSet the planning time fence to 10 days in the corresponding product heuristic.
- DSet the planning time fence to 10 days in the corresponding ECC MRP group.
- ESet the firming date in the ECC stock/requirements list to 10 days in the future.
How the community answered
(71 responses)- A3% (2)
- B82% (58)
- C6% (4)
- E10% (7)