A customer defines a variant for a production planning run and needs to specify the planning objects for the SAP_MRP_002 heuristic. They ask you for the appropriate selection criteria. Which of the…
The correct answer is C. Products. See the full explanation below for the reasoning.
Question
A customer defines a variant for a production planning run and needs to specify the planning objects for the SAP_MRP_002 heuristic. They ask you for the appropriate selection criteria. Which of the following planning objects do you recommend?
Options
- AResources
- BOperations
- CProducts
- DOrders
How the community answered
(15 responses)- A7% (1)
- B7% (1)
- C73% (11)
- D13% (2)