A customer defines a variant for a production planning run and needs to specify the planning objects for the SAP_MRP_002 heuristic. They ask you for the appropriate selection criteria. Which of the…

The correct answer is C. Products. See the full explanation below for the reasoning.

Question

A customer defines a variant for a production planning run and needs to specify the planning objects for the SAP_MRP_002 heuristic. They ask you for the appropriate selection criteria. Which of the following planning objects do you recommend?

Options

  • AResources
  • BOperations
  • CProducts
  • DOrders

How the community answered

(15 responses)
  • A
    7% (1)
  • B
    7% (1)
  • C
    73% (11)
  • D
    13% (2)