You want to define virtual safety stock within PP/DS. Which statements correctly describe this kind of modeling? Note: There are 3 correct answers to this question.

The correct answer is A. The virtual safety stock is only "virtually" visible for the MRP run and is not included in the B. The virtual safety stock requires a separate PP/DS heuristic to become visible as a E. The virtual safety stock logic can only be defined for an entire planning version. See the full explanation below for the reasoning.

Question

You want to define virtual safety stock within PP/DS. Which statements correctly describe this kind of modeling? Note: There are 3 correct answers to this question.

Options

  • AThe virtual safety stock is only "virtually" visible for the MRP run and is not included in the
  • BThe virtual safety stock requires a separate PP/DS heuristic to become visible as a
  • CThe virtual safety stock is only considered in the dynamic pegging logic.
  • DAs soon as the material master has a safety stock value assigned, a virtual safety stock is
  • EThe virtual safety stock logic can only be defined for an entire planning version.

How the community answered

(37 responses)
  • A
    78% (29)
  • C
    8% (3)
  • D
    14% (5)

Community Discussion