You can store transactional data in APO in liveCache as time series or orders. You can also back this data up to BW. Which transaction is described correctly?
The correct answer is B. /SAPAPO/MC90: "Release Demand Planning to Supply Network Planning" converts time. See the full explanation below for the reasoning.
Question
You can store transactional data in APO in liveCache as time series or orders. You can also back this data up to BW. Which transaction is described correctly?
Options
- A/SAPAPO/LCOUT: "Release to Demand Planning" converts time series to orders
- B/SAPAPO/MC90: "Release Demand Planning to Supply Network Planning" converts time
- C/SAPAPO/REL_TO_SNP: "Release from InfoProvider to Supply Network Planning" converts
- D/SAPAPO/TSCUBE: "Load Data from InfoCube" loads orders and time series into BW
How the community answered
(39 responses)- A5% (2)
- B77% (30)
- C13% (5)
- D5% (2)