Why would you use an SNP PDS instead of an SNP PPM?

The correct answer is C. You can transfer a production version in ECC directly as an SNP PDS. See the full explanation below for the reasoning.

Question

Why would you use an SNP PDS instead of an SNP PPM?

Options

  • AThe SNP PDS can be maintained in SCM APO.
  • BThe SNP PDS contains more parameters to steer supply network planning.
  • CYou can transfer a production version in ECC directly as an SNP PDS.
  • DYou can use the SNP PDS to support change management within SNP.

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    16% (8)
  • C
    71% (36)
  • D
    10% (5)