Question

The customer wants to implement safety stocks dependent on forecast accuracy and replenishment lead time accuracy. Quantity-based complete deliveries are needed. What do you have to do to achieve this? Note: There are 2 correct answers to this question.

Options

  • AConfigure the SSP planning run and schedule after the SNP planning run.
  • BDefine the DP key figures from which the system can derive forecast accuracy and
  • CIn the product master, maintain the safety stock method BS (Beta service level and reorder
  • DIn the product master, maintain the safety stock method AS (Alpha service level and reorder
  • ECreate a safety stock planning (SSP) profile and select lead time calculation by critical or