When can you use more than one check instruction during order creation? Note: There are 3 correct answers to this question.

The correct answer is A. During an ATP check with different check modes because of hard coded business events. B. During location determination in a rules-based availability check, using an activity for location C. During a substitution of the requested location product. See the full explanation below for the reasoning.

Question

When can you use more than one check instruction during order creation? Note: There are 3 correct answers to this question.

Options

  • ADuring an ATP check with different check modes because of hard coded business events.
  • BDuring location determination in a rules-based availability check, using an activity for location
  • CDuring a substitution of the requested location product.
  • DDuring location determination in a rules-based availability check, using a calculation profile.
  • EDuring an ATP check with different ATP profiles determined in ECC.

How the community answered

(24 responses)
  • A
    75% (18)
  • D
    8% (2)
  • E
    17% (4)