SAP
C_TSCM42_66 · Question #9
C_TSCM42_66 Question #9: Real Exam Question with Answer & Explanation
Sign in or unlock C_TSCM42_66 to reveal the answer and full explanation for question #9. The question stem and answer options stay visible for context.
Question
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: - Start: 7:00:00 a.m. - End: 3:00:00 p.m. - Break duration: 1 hour - Rate of utilization: 80% - Overload: 110% - Number of individual capacities: 1 How large is the standard available capacity?
Options
- A8 hours
- B5.6 hours
- C6.16 hours
- D7 hours
Unlock C_TSCM42_66 to see the answer
You've previewed enough free C_TSCM42_66 questions. Unlock C_TSCM42_66 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.