In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: - Start: 7:00:00 a.m. - End: 3:00:00 p.m. - Break duration: 1 hour - Rate of…
Sign in or unlock C_TSCM42_66 to reveal the answer and full explanation for question #9. The question stem and answer options stay visible for context.
Question
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
Options
- A8 hours
- B5.6 hours
- C6.16 hours
- D7 hours