In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization…

The correct answer is C. 5.6 hours. See the full explanation below for the reasoning.

Question

In SAP ECC, you calculate the standard available capacity for a work center capacity with the following data: start: 7:00:00 a.m., end. 3:00:00 p.m., break duration: 1 hour, rate of utilization:

80%, overload. 110%, number of individual capacities: 1. How large is the standard available capacity?

Options

  • A7 hours
  • B8 hours
  • C5.6 hours
  • D6.16 hours

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    6% (1)
  • C
    76% (13)
  • D
    12% (2)