C_TSCM42_66 · Question #71
After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials). Which of the following planning file entries for this material are set by the…
The correct answer is C. The BOM explosion, the NETCH, and the NETPL planning indicators. See the full explanation below for the reasoning.
Question
After a material has been included in a NETCH material requirements planning run you change its BOM (bill of materials). Which of the following planning file entries for this material are set by the system?
Options
- AThe BOM explosion and the NETPL planning indicator
- BThe BOM explosion indicator
- CThe BOM explosion, the NETCH, and the NETPL planning indicators
- DThe NETCH and NETPL planning indicators
How the community answered
(17 responses)- A18% (3)
- B6% (1)
- C71% (12)
- D6% (1)