C_TSCM42_66 · Question #58

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these…

The correct answer is B. Handling existing procurement proposals within a planning time fence. D. Handling new procurement proposals that need to be created due to new requirements within the planning. See the full explanation below for the reasoning.

Question

In the Customizing for requirements planning, a project team notices that the alternatives P1, P2, P3 and P4 are also delivered as standard in addition to MRP type PD. The number in each of these alternatives represents a firming type. What does a firming type define? (Choose two)

Options

  • AHandling existing procurement proposals outside the planning time fence.
  • BHandling existing procurement proposals within a planning time fence.
  • CHandling new requirements within the planning time fence.
  • DHandling new procurement proposals that need to be created due to new requirements within the planning

How the community answered

(33 responses)
  • A
    12% (4)
  • B
    82% (27)
  • C
    6% (2)