C_TSCM42_66 · Question #54

You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence. What do you have to consider in this scenario?

The correct answer is D. Planned orders that are created by requirements planning are shifted to the end of the planning time. See the full explanation below for the reasoning.

Question

You use a planning time fence and fixing type 1. You receive a customer order with a material availability date within the planning time fence. What do you have to consider in this scenario?

Options

  • ARequirements planning considers only changes that are relevant for scheduling within the planning time
  • BPlanned orders are created within the planning time fence and automatically firmed by requirements
  • CThe MRP controller cannot create planned orders within the planning time fence.
  • DPlanned orders that are created by requirements planning are shifted to the end of the planning time

How the community answered

(41 responses)
  • A
    10% (4)
  • B
    15% (6)
  • C
    2% (1)
  • D
    73% (30)

Community Discussion

No community discussion yet for this question.