Question
What sequence do you follow in master data maintenance to define the production of a material?
Options
- ACreate work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
- BCreate routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or
- CCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
- DCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or