What sequence do you follow in master data maintenance to define the production of a material?
The correct answer is D. Create BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or. See the full explanation below for the reasoning.
Question
What sequence do you follow in master data maintenance to define the production of a material?
Options
- ACreate work centers -> Create routing -> Create BOM -> Carry out component assignment in work center
- BCreate routing -> Create work centers -> Create BOM -> Carry out component assignment in BOM or
- CCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in work center
- DCreate BOM -> Create work centers -> Create routing -> Carry out component assignment in BOM or
How the community answered
(31 responses)- A16% (5)
- B3% (1)
- C6% (2)
- D74% (23)