Which of the following master data is necessary for the creation of material reservations for production orders?
The correct answer is A. Material master records. See the full explanation below for the reasoning.
Question
Which of the following master data is necessary for the creation of material reservations for production orders?
Options
- AMaterial master records
- BProduction/resource tools
- CRoutings
- DProduction versions
How the community answered
(46 responses)- A72% (33)
- B4% (2)
- C7% (3)
- D17% (8)