C_TSCM42_66 · Question #39

During the processing of production orders planned and actual costs are determined. On which of the following objects can you collect these costs? (Choose two)

The correct answer is A. Production order B. Product cost collector. See the full explanation below for the reasoning.

Question

During the processing of production orders planned and actual costs are determined. On which of the following objects can you collect these costs? (Choose two)

Options

  • AProduction order
  • BProduct cost collector
  • CWork center
  • DPlanned order

How the community answered

(32 responses)
  • A
    78% (25)
  • C
    9% (3)
  • D
    13% (4)

Community Discussion

No community discussion yet for this question.

Full C_TSCM42_66 Practice